THE
DESIGN AND FEATURES OF SHUIBUYA CFRD
Liu Zhaohui
Shuibuya 233m high CFRD
at Qingjiang River is the highest of its kind in the world. The settlement of
dam and crack resistance of face slab must be controlled strictly. Based on
detailed studies made to the dam structure, construction materials and its
foundation treatment, the dam is possessed with the following main features:
(1) the main rockfill is inclined from the cross of dam axis with crest toward
downstream in a slope of 1:0.2; (2) the design indices for dry density and
porosity of material on each zone is of high standard; (3) the adoption of
standard plinth with extended seepage-proof board; (4) a downstream RCC
cofferdam is integrated with the dam; (5) fully use of materials from structure
excavation;(6) only partial removal and ramming is adopted for riverbed cover.
Key Words: Shuibuya Project CFRD
Structure Foundation
treatment
1
Geology and topography
Shuibuya dam is located at a “S”-shaped part about 800m long in the
middle stream of the Qingjiang River. The river valley at the damsite is
unsymmetrical, slopes of both banks are steep in topography, the overall angle
of slope on the left bank is about 52°, and the average slope angle at the
right bank is 35°. The riverbed elevation at the damsite is about 193~107m, and
the valley width at the dam axis at crest elevation 409m is about 560m. Bazigou
Gulley located at the upstream on the right bank of the dam has materially
impact on the layout of plinth.
The strata of the dam
site slopes gently dip upstream and slant toward the left bank at 7~12°. Major strata include Maokou Group (P1m) and Qixia
Group (P1q) of the lower Permian. Longtan Group (P2l) of the upper Permian also
distributed on elevation above 395m at the left abutment with the Quaternary
debris, collapsing sediment, flood sediment and a few artificial deposits
distributed at bank slopes and the riverbed.
The riverbed at the
damsite is generally flat with thin coverage, but also with some deep trenches.
The thickness of coverage is around 1.48~21.7m, which is thick around the
centerline and gradually reduced toward both banks. The riverbed coverage is
comprised of washing debris, collapsing sediment, flood sediment and artificial
deposits. Riverbed washing debris is composed of scree stratum, grit stratum
with piece rock together with grit silt and clay lens strata. Geological survey
shows that the riverbed sand scree stratum is of loose to middle density
structure, with low loading capacity on washing, low deformation modulus and
high compressibility.
2 Dam
zoning and rockfill material design
Shuibuya CFRD is 233m
high with crest elevation at el.409m, crest width 12m, dam axis length 608m,
the river direction length from upstream plinth to downstream RCC cofferdam
616.2m, dam filling volume about 15.3 million m3.
1.2.1
Dam zoning
Under the premise of safety operation, in considering of the working state, stress distribution, source of material and hydraulic features of the dam, proper zoning on dam filling materials is carried out to take the fully utilization of material from structure excavation and to simplify construction. The principle for dam zoning is: 1) the part upstream the dam axis is the main loading zone, higher deformation modulus is required for rockfill in this zone, lower value can be adopted for the part downstream the axis; 2) material in each zone shall meet the requirement on hydraulic transit and the permeability coefficient shall be kept on increasing from upstream to downstream; 3) take full utilization of material from structure excavation to reduce the cost; 4) satisfactory with mechanical construction. The dam zoning is shown as following (see Fig.1):

Fig.1 Shuibuya Dam Zoning
(1) IA zone (fine sand cover): Its function is to
block any crack on the slab and to restore the impermeability by entering the
crack with flow in case partial crack or damage in water stop system. The crest
elevation of fine sand material is 263.0m, horizontal width 3.0m.
(2) IB zone (cover zone): Its function is to
protect fine sand material not be scoured and eroded. The crest elevation of
cover zone is 265.0m, crest width 15.0m, upstream slope 1:2.5.
(3) IIA zone (filter zone): Filter zone is located
underneath the slab. Its function is to provide even and flat support surface
for slab, to counter-filtering upstream curing material and control the seepage
in case partial crack or damage in water stop system. Filter material is
equally arranged in 4.0m wide. A 2.0m thick filter material also placed on the
contact with foundation rock in upstream 1/3 head range.
(4) IIAA zone (fine material zone): In order to
provide more compact, even and flat support surface for the bottom copper water
stop at perimeter joint, and enhance the control of filter material on seepage,
such a zone is arranged underneath the perimeter joint. The zone is shaped in
trapezoid, minimum thickness at top is 3.0m, downstream slope 1:1.4.
(5) IIIA zone (transient zone): It is for the
hydraulic transient between filter material and main rockfill. It is arranged
in equal width of 5.0m horizontally. To prevent void in the contact with bank
slopes, a 2.0m thick transient zone is arranged at the contact of main rockfill
with dam foundation.
(6) IIIB zone (main rockfill zone): It is the main
support for water load located in the upstream of dam axis. The boundary of
main rockfill and secondary rockfill is in the slope of 1:0.2 from dam axis
down to the riverbed.
(7) IIIC zone (secondary rockfill zone): To take
full utilization of material from structure excavation, secondary rockfill is
arranged at the downstream of main rockfill from el.225.0m to el.380.0m. The
crest is 29.0m wide and the boundary slope with IIID zone is of 1:1.4.
(8) IIID zone (downstream rockfill zone): For
secured dam drainage and the stability of downstream dam slope, downstream
rockfill zone is placed in the scope below el.225.0m from the secondary rockfill
zone and 10m to the downstream dam slope. The downstream slope is protected
with 1.0m thick stone blocks paved by dry masonry.
To secure the stability
of downstream dam slope and to facilitate overtop during flood season in
construction period, a RCC cofferdam is built at the downstream toe as a part
of the dam.
2.2
Design of dam material
(1) Filter material (IIA): Filter material requires
sound gradation, low compressibility, high shear strength, adequate
permeability and good construction performance. Filter material is processed
from limestone of Maokou Group, maximum diameter dmax ≤80mm,
the content of d<5mm 35%~50%, the content of d<0.1mm 4%~7%, permeability
coefficient 10-2~10-4 cm/s, design dry density 2.25 g/cm3, porosity 17%. Layer
thickness for compaction 40cm.
(2) Fine material (IIAA): The maximum diameter of
fine material is smaller than filter material so as to function as
counter-filtering on curing of cracks. The fine material is obtained by
removing particles with d> 40mm from filtering material. dmax ≤40mm, the content of d<5mm 35%~60%, the content
of d<0.1mm 5%~10%. Layer thickness for compaction 20cm.
(3) Transient material (IIIA): Transient material
is taken from the blasting limestone of Maokou Group and tunnel excavation from
the 4th and 5th formation of Qixia Group (P11q, P51q). dmax ≤300mm, the content of d<25mm less than 50%, the
content of d< 5mm 20%~30% and the content of d<0.1mm less than 5%. Design
dry density 2.19 g/cm3, porosity 18.8%, permeability coefficient 100~10-1 cm/s.
Layer thickness for compaction 40cm.
(4) Main rockfill (IIIB): Limestone of Maokou Group
with high compression modulus and high shear strength is used for the main
rockfill. dmax <800mm, the content of d<0.1mm less than 5%, and
continuous gradation is required, permeability coefficient shall be higher than
100 cm/s. Design dry density 2.18 g/cm3, porosity 19.6% . Layer thickness for
compaction 80cm.
(5) Secondary rockfill (IIIC): Limestone of Qixia
Group from structure excavation is used for the secondary rockfill. dmax
<800mm, the content of d< 5mm 20%, the content of d<0.1mm not higher
than 5%, and continuous gradation is also required. Design dry density 2.15
g/cm3, porosity 20.7%. Layer thickness for compaction 80cm.
(6) Downstream rockfill (IIID): Downstream rockfill
can be limestone from Qixia or Maokou Group, dmax <800mm, the content of
d<0.1mm less than 5%, permeability coefficient shall be higher than 100
cm/s. Design dry density 2.10 g/cm3, porosity 20.7%. Layer thickness for
compaction not higher than 80cm.
3.
Design of plinth, slab and water stop
3.1
Plinth
In order to reduce
plinth excavation at both banks, the structure of a standard plinth with
extended seepage-proof board is adopted in Shuibuya dam. The foundation of the
plinth is of weak load-relief zone or treated strong load-relief zone. The
thickness of plinth (standard plinth plus extended seepage-proof board) is
defined by the allowing gradient of permeability. Standard plinth is generally
6~8m wide, 0.6~1.2m thick, and the extended seepage-proof board is generally 4~12m
wide, 0.3m thick. A settlement joint with water stop is furnished between the
standard plinth and the extended seepage-proof board. The plinth is divided
into riverbed, left and right bank three sections.
Single layer two-way of
reinforcing bar is placed in the plinth concrete, reinforcing rate is about
0.35%, the reinforcing net is connected to foundation rock through anchors.
To eliminate possible
crack on plinth concrete, during the construction of standard plinth, a 2m wide
groove is left in every 12~16m, then is backfilled with low heat inflation
cement when the temperature of plinth concrete is basically stable.
3.2
Slab
The thickness of slab
is defined by equation T=0.3+0.0035 H (H is the height to dam crest) with
minimum thickness 0.3m at the top and maximum 1.1m at the bottom. The slab is
16.0m wide at compressive zone and 8.0m at tensile area, and is divided into 38
construction blocks, total area is 134 thousand m2. The slab is
adopted with single layer two-way of reinforcing. The reinforcing rate at slope
direction is about 0.4% and about 0.35% in the direction of dam axis. Enhanced
reinforce bar is placed around perimeter joint as well as tensile construction
joints.
In order to reduce horizontal and vertical restraints of filtering material on the slab, a layer of emulsified asphalt is sprayed on the filter. High efficient additives such as enhancing denser are mixed into the concrete to improve the performance of slab against crack. The compressive strength of concrete below el. 346m is of R90350# and R90300# above el.346m. Tensile limit is not less than 10-4, classification in anti-seepage is of S12 and D250 for anti-freezing.
3.3
Water stop
Three water stops is
adopted at perimeter joints below el. 350m, where the bottom and middle water stops
are of copper water stop, the top water stop is comprised of a rubber stick
banded with rubber ripple water stop and is filled with flexible materials in
between. Flexible material is also placed above the ripple water stop and is
sealed by reinforced rubber strip on the surface. For perimeter joints above
el.350m, only the same structured bottom and top water stops are placed. The
external surface of perimeter joints is placed with non-sticky fine material
for self-curing.
As it is difficult to
predict precisely the compressive and tensile features of vertical joints on
the slab and to secure the integrity of water stop system, all vertical joints
are designed based on tensile, namely bottom copper water stop and top water
stop of flexible material are placed. For slab contacted with perimeter joint
below el. 350m, middle water stop is also installed for vertical joints of the
slab in the range of 5m to perimeter joint so as to ensure the tightness of the
middle water stop in the perimeter joint.
4.
Foundation Treatment
4.1
Disposal of Riverbed Cover
The riverbed cover is
of loosen to middle dense structure, washing sediments such as gravel and grit
are of low loading capacity (Pk 280~770kPa), low deformation modulus (E0
24.3~73.25 Mpa). There are also some grit silts and clay lens in the riverbed
cover of the straight section downstream the dam axis. These lens strata are
also featured with multiple layers of distribution. Based on investigation, it
is decided to remove the riverbed cover within the scope of 180m down from
riverbed plinth line and 100m upstream of the downstream cofferdam. Part of the
cover remained will be compacted so as to reduce dam settlement.
Based on site compact
test, it is decided to use a 2.2m diameter, bottom area 3.8m2 and
20.8t weight rammer in a ramming span of 5m x 5m, falling distance of 15m and
312tm of ramming force as the construction parameters. The riverbed cover will
be rammed for 2 passes, the first pass will be rammed in span by 8~10 times;
the second pass will be rammed with low energy in full range by 2~4 times. For
quality control, the settlement between last two strikes shall not be greater
than 5cm.
4.2
Curtain Grouting
Shuibuya dam foundation
is comprised of karstified strata of Maokou Group and Qixia Group limestones
and interbeds of marlite in lower Permian. Faults and load relief zone are
developed on both banks and with multiple karst passages. Terranes in the
damsite area is flat with weak interbeds such as shear zones well developed. As
the curtain of riverbed section is carried out on the plinth which is only
0.6~1.2m thick, it is of grouting with heavy cover. Comparing with more than
200m of head and such complicated geological condition, it is a challenge for
both design and construction of the curtain.
Under the premise that
no uplift damage to the plinth is secured, it is very important to increase the
grouting pressure, especially the pressure for shallow foundation. Based on
site grouting test, with the consolidation of anchor to enhance the effect of
consolidation grouting, optimized construction method and process for grouting,
the final formation of curtain can be secured.
Consolidation grouting
is required for the foundation of both standard plinth and the extended
seepage-proof board before curtain grouting. In order to ensure the effect of
consolidation grouting, the grouting is carried out in two steps, and the
grouting hold for the foundation of standard plinth is arranged in cinquefoil,
span 2m, depth 5~7m. The grouting hole for the consolidation of extended
seepage-proof board is also arranged in cinquefoil with 2m span and 5m in
depth. The maximum pressure for the first section (contact section) of
consolidation grouting shall be 0.3~0.5Mpa.
The curtain-grouting
hole for the foundation of plinth is also arranged in cinquefoil with a span of
2m. 4 rows of holes are arranged in the lower part of the plinth, where row 2
and 3 are of main curtain grouting holes need to be constructed in three steps,
row 4 is of auxiliary curtain grouting holes, which will be constructed in two
steps. The pressure for curtain grouting is 1.5~4Mpa.
5.
Features in the Dam Design
During the bidding
design of Shuibuya dam, the design scheme in feasibility study is further
optimization and finalized with the flowing main features:
(1) Main rockfill is inclined from the cross of dam
axis with crest toward downstream in a slope of 1:0.2, which is favorable for
even settlement and the control of the total settlement in the dam;
(2) The design indices for dry density and porosity
of material on each zone is of high standard, which is favorable for the
control of settlement;
(3) The adoption of standard plinth with extended
seepage-proof board is favorable for dam filling speed and the reduction in
plinth excavation;
(4) Downstream RCC cofferdam integrated with the
dam is good for both the stability of downstream slope and the protection in
case of overtopping;
(5) Take the full use of materials from structure
excavation which shows the advantage of local material supply and design the dam
according to local availability in the design principle of local material dam
by using 8 millions m3 of excavation from the spillway;
(6) Based on scientific test, partial removal and
ramming of riverbed cover is adopted.